Q: Is there a total estimate aer/ug footage for the project?

As the project boundaries are still developing, there is not a current total. Please send in the NDA to obtain shape files of current project boundaries and footages.

Q:Is there an anticipated footage to be on US Naval Reservation, wetlands, state parks, or other area that will require special permitting?

A:We would stop short at the Naval and Park entrance where we currently have our Primary Meter. Engineering Company will need to obtain wetland permits.

Q: Does the PUD intend to utilize any existing assets/leased fiber? If so, what is the estimated footage?

A: Yes – approximately 17 miles between Quilcene and Discovery bay.

Q: What is the total HHP?

A: As the project boundaries are still developing, there is not a current total. Please send in the NDA to obtain shape files of current project boundaries and footages.

Q: Will pole loading be done by engineering contractor, PUD, or third party?

A: TBD

Q: Will as-built drawings/PDF be required or will GIS data only be acceptable?

A: As-builts can be done in GIS only

Q: What fiber management system does PUD currently use?

A: TBD